AHU PROJECT

Deadline : 2 Weeks
As part of a major site refurbishment and site shut down, Aquaflow were tasked with replacing the existing mild steel LPHW pipework from main riser to AHU heater battery coil.

Scope of work;
Decommission existing kitchen supply AHU on external mezzanine atrium roof.
Isolate and drain down existing LPHW services, cut out and remove.
Cut back high level LPHW flow and return pipework in ceiling and install new copper pipework from inside to outside incorporating new isolation and control valves.
Lag all new pipework with waterproof black PIB sheeting.
Commission and test.

 

Credit : John Weatherley

EMPLOYEE OF THE MONTH – SEPTEMBER

 

For most of us, the EOTM award this month being given to DAVID WALSH will not come as a surprise, given that he has had votes every month since we started this and truly deserved this bonus and acknowledgment of his efforts. David is always putting in 100% to his work and is a very popular and respected member of team.

Congratulations Walshy, you have had some very kind comments from all and this is very well deserved.

Keep up the good work, you are a great asset to AquaFlow.